Contract D, located in Branford, consists of the reconstruction of approximately 2.1 miles of I-95 from the western project limit at the eastern abutment of the Lake Saltonstall Bridge to the eastern project limit at Interchange 54 (Cedar Street).

The completed reconstruction provides three travel lanes in each direction, increased shoulder widths and a new median barrier throughout the project. The project includes two new retaining walls, replacement/rehabilitation of two bridges, three culverts, new drainage systems, signing, lighting and noise barrier walls as well as improvements to Cedar Street (Interchange 54) and a new commuter parking lot at Interchange 55.

Contract D1, located in Branford and East Haven, included final milling, paving and striping of I-95 SB in the Contract D area. Also, resetting catch basins and guide rail as well as milling, joint replacement and repaving of Bridge No. 00186 (I-95 over Lake Saltonstall). Installation of Right-of-Way fencing and wetland mitigation plantings in Branford as well as installation of noise barrier wall in the vicinity of the Farm River in East Haven were also included in this project.

 

Explore Further:

Traffic Image Photo Gallery >
See Contract D/D1 Photos as well as other Program Photos.
Traffic Image Interactive Map >
Get the latest information on traffic alerts and detours.