|
Last Updated: November 4, 2011
Project Name, Contract Number: Contract E1, State Project 92-581
Project Area: Soil Preloading and Settlement Monitoring
Project Scope: Contract E1 consisted of the construction of soil preloading, soil settlement monitoring, and associated drainage and utility relocations required to complete the proposed roadway and bridge improvements for the new I-95/I-95/Route 34 Interchange. Installation of test piles, pile load tests and vibration/settlement testing/analysis of the Cowles Building were also included.
Project Designer: H.W. Lochner
Project Contractor: L. G. DeFelice, Inc.
Contract Milestones:
Begin Construction - November 12, 2004 Finish Construction- December 15, 2006
Progress Summary:
Construction of Contract E1 is complete.
|