Last Updated: November 9, 2011
Project Name, Contract Number: Contract B, State Project No. 92-532
Project Area: Pearl Harbor Memorial Bridge
Project Scope: Contract B consists of the replacement of the existing Pearl Harbor Memorial (Q) Bridge with a new extradosed 10 lane signature bridge. The project encompasses approximately 1,300 meters (0.8 miles) of I-95 from the western project limit at the abutment at East Street and Hamilton Street to the eastern project limit at the Stiles Street abutment. Five travel lanes will be provided in each direction from the bridges west approach to a reconfigured/combined Woodward Avenue/Stiles Street interchange at the east approach. The new Pearl Harbor Memorial Bridge will be extended to include the Stiles Street overpass. Full shoulders, a new median barrier, drainage, signing, and lighting will be provided throughout the project.
Project Designer: URS Corporation
Project Contractor: Walsh Contruction Co / PCL
Contract Milestones:
Contract Award: July 31, 2009 Notice to Proceed - Part 1 (Administrative): September 14, 2009 Notice to Proceed - Part 2 (Construction): November 27, 2009 Construction Completion Date: June 30, 2015
Progress Summary:
Construction activities for October 2011 included:
- Deck pours continued for the I-95 NB approach to Anchor 1 and are scheduled to be complete by the end of November.
- Continued concrete pours for bridge deck segments spanning the Quinnipiac River. The first seven deck segments are complete on the Tower Piers.
- Began installation of cable stay pipes, which will house the cable stays. The first cable stay is currently scheduled to be installed in November.
Milestones:
- The first cable stay installation is scheduled to occur in November 2011.
See Photo Gallery link to the right for recent photos.
|